The rebuilt section of Custer Parkway in north Richardson is getting its final pavement markings, one of three road jobs the city flagged for drivers late last week.
Crews started striping the new roadway between Canyon Creek Drive and Renner Road and expect to keep at it throughout November, the city said in a Nov. 6 update. The markings return the street to the layout it had before construction: one travel lane in each direction plus a dedicated bike lane.
The city asked drivers to follow the new lines and stay out of the lanes marked for bicycles.
Greenville Avenue near downtown
Northbound Greenville Avenue loses its right lane between Huffhines Street and Polk Street on some days while Oncor installs two power poles. The closure can run from 9 a.m. to 3:30 p.m., and the city says the work should wrap up by mid-January, weather permitting.