Back to Richardson

Custer Parkway's southbound side near Canyon Creek set to reopen this month as Lookout Drive lights stay dark

Richardson says new southbound pavement between Lookout Road and Canyon Creek Drive should carry traffic in October, while Oncor still has no timeline for restoring streetlights along Lookout Drive.

Renata Ferris

October 5, 20262 min read

Roadwork cones and streetlights - illustration, Jake Team LLC

Drivers who have spent nearly two years squeezed into single lanes on Custer Parkway should see another piece of the road open this month, according to a project update the City of Richardson posted Friday afternoon.

New pavement between Lookout Road and Canyon Creek Drive is close to finished, and the city expects the southbound side of that stretch to take southbound traffic sometime in October. Once drivers move over, crews will go back to the median to plant, install irrigation and repair the grass strips along the curbs.

Streetlights out on Lookout

The same update acknowledged a separate problem for people living near the corridor: several streetlights along Lookout Drive are out. The city said it has asked Oncor to explain what knocked the lights out and when they might return, and that Oncor's contractors are still trying to pin down the cause.

As of Friday, the city said, there was no timeline for getting the power back.

Streetlights on Custer itself are being replaced as part of the project. Oncor is due to put up the permanent fixtures near the end of the project.

Where the work stands

The city laid out the rest of the schedule segment by segment:

  • Pleasant Valley Drive to Lookout Road: crews are planting and irrigating the median and restoring the parkways, and expect to finish by late October.
  • Canyon Creek Drive to Campbell Road: pavement replacement continues and is expected to wrap up in November, provided the weather cooperates and there are no more delays from franchise utilities.
  • Overall: substantial completion is expected around the end of 2026, with smaller repairs and replacements carrying into early next year.

What drivers will see now

From Renner Road south to Lookout Drive, traffic runs one lane each way on the new pavement while the inside of the road stays closed for the last round of median work.

At Campbell Road, both directions are running on the new northbound side of Custer, one lane each way. The city warned of more lane shifts and closures where Custer meets Campbell, both to finish the median and to make room for an upcoming Atmos Energy gas line relocation.

Closures are also expected at Renner Road and Custer, where crews still have corner ramps, sidewalks and median work to complete.

DDM Construction holds the contract to rebuild Custer Parkway from Campbell Road to State Highway 190, and work on the first segments began in November 2024. The project, paid for through Richardson's 2021 bond program, has moved traffic from side to side several times as crews replaced waterlines, sewer and storm drains before laying new pavement.

Updates are posted on the city's project page at cor.net/CusterParkway.