Drivers heading north on Custer Parkway who turn left onto Lookout Drive will find the dedicated turn lanes closed at times starting as early as Monday, Nov. 30, the city said in a construction update posted Wednesday.
The work is part of the Custer Parkway Improvement Project and is expected to take two to three days. Closures will be limited to off-peak hours, between 9 a.m. and 3:30 p.m. Outside those hours, crews will cover any openings in the pavement with steel plates so the turn lane can reopen.
Finding the fiber first
Crews will core the pavement to pinpoint underground fiber-optic utility lines at the intersection. The city said that step has to happen before an irrigation waterline can be installed beneath the intersection to water the landscaping planned for the project's medians.
Once the existing lines are located, the irrigation line will go in by underground boring, and the city does not expect more lane closures for that part of the job.
Project details are posted at cor.net/CusterParkway.